- Construction Progress |
- Construction Photos
Major Works (West Tower)
• Rectification Works on 6th to Upper Penthouse
• Construction of Electrical Pedestal and Feeder Lines
• Installation of Tiles on the T&B of 9th to Upper Penthouse Level
• Installation of Water Tanks and Pumps
• Installation of Curtain Walls at Penthouse
• Painting Works at 9th to Upper Penthouse Level
• Fire Protection Works at Site Development and TP Plus
Major Works (North Tower)
• Installation of sanitary pipes from 10th -15th floor.
• Installation of toilet exhaust duct from 9th -14th floor
• Installation of smoke extraction duct from 8th to 14th floor
• Installation of BI pipe (cross main) for fire protection works at 5th to 10th floor
• Installation of wooden door jambs from 10th to 14th floor
• Masonry works from twelfth to fifteenth floor
• Plastering works from ninth to eleventh floor
• Installation of Aircon Ledges from 5th -8th floor